Share This Article
While North Arkansas Electric Cooperative’s internet service racked up $7.6 million in profits last year, its electric division lost $2 million—the second straight year of losses that led to a 9.4% rate increase for members.
The financial divide between the two operations was laid bare during last Thursday’s annual meeting, where executives spent hours explaining why the profitable fiber subsidiary couldn’t bail out the struggling electric side.
Next, the cooperative’s broadband service, has exploded from 750 customers in 2018 to 21,276 today. Two-thirds of NAEC’s electric members now subscribe to the internet service, far exceeding the 20-30% the cooperative originally expected.
“It’s been wildly successful,” said Scott Hamby, Next’s chief operating officer.
But success on one side hasn’t translated to the other. The electric division posted negative operating margins of $1.1 million in 2023 and $2 million in 2024.
“If it were not for Next, the co-op would have had to have a rate increase probably two years ago,” said Mike Dover, a member who spoke in defense of the board’s decisions during the rate increase discussions.
The Fiber Success Story
Hamby presented Next’s growth statistics to members at the Fulton County Fairgrounds meeting.
The service that started as a pilot program in 2016 to prove financial viability has become “the largest fiber-based ISP within our seven-county footprint,” according to Hamby. “Other than cellular, Next is the largest ISP in these seven counties.”
Growth has been explosive: 16,392 customers at the end of 2022, 19,420 by the end of 2023, and 21,276 as of June 2025. The 67% take rate among cooperative members far exceeds original projections.
The subsidiary turned profitable in 2022, helped by federal grants from the Connect America Fund and Rural Digital Opportunity Fund. Of the $7.6 million in 2024 margins, $5.7 million came from federal broadband grants set to expire between 2029 and 2032.
Customer satisfaction is high—95% of new subscribers say they would recommend the service. The cooperative even gave its 20,000th subscriber in Horseshoe Bend free internet for life.
“Without our employees, we would not be who we are today,” Hamby said, praising the 15 full-time Next employees. “They truly pour their heart and soul into this company.”
The Electric Division’s Struggles
While Hamby celebrated Next’s success, Chief Financial Officer Julie Haney delivered sobering news about the electric side during a presentation that had some members shifting in their seats.
“Operating margins from the electric division were negative 1.1 million and 2 million, respectively,” Haney said. “This caused a significant decline in what’s called the operating times interest earned ratio.”
The problems are mounting:
- Right-of-way maintenance costs jumped from $1.8 million in 2019 to $4.6 million annually—a 153% increase
- Transformer prices rose 40% in two years
- Circuit breakers cost 50% more
- March tornadoes caused $6 million in damage with no FEMA reimbursement expected
- The cooperative added just 181 new electric members in 2024, a 0.6% growth rate
Without Next’s profits propping up the overall finances, the cooperative would have failed its debt service requirements. A key financial metric called OTIER dropped from 2.23 in 2022 to 1.54 in 2024, dangerously close to the 1.10 minimum required by lenders.
“If you calculated OTIER with only the electric division, OTIER would have been at 1.01 and 0.84 at December 2023 and 24, respectively,” Haney said. “Not only would we have failed our OTIER in 2023 without fiber, but also our debt service coverage ratio.”
Why Can’t Fiber Bail Out Electric?
The question frustrated members throughout the meeting: If Next is making millions, why are electric rates going up?
The answer lies in regulatory requirements. The Arkansas Public Service Commission requires that electric rate studies exclude revenue and expenses from other services like broadband.
“It would be a concern by the public service commission and our members if the electric rates subsidized fiber or vice versa,” Haney explained.
The setup is complex. NAEC owns the 3,600 miles of fiber network and 23,000 individual connections. Next leases this infrastructure from the electric cooperative and pays rent. But that rent is set by market rates, not by what might help electric customers most.
Steve Hall, a former NAEC employee who presented proposals at the meeting, later wrote online that CEO Mel Coleman “refused to even consider adjusting fiber rental costs to benefit the electric division.”
During the meeting, member Tim Howsman pressed the issue, asking why the cooperative couldn’t increase the interdepartmental rent to shift more money from Next to the electric side.
Coleman defended the current structure: “Next was not designed to take the place of what we collect in rates. It did a really good thing because it bridged the gap in this time period where our OTIER started deteriorating.”
Different Missions, Different Results
The two divisions emerged from different needs. Next launched to bring high-speed internet to rural areas where commercial providers wouldn’t invest, much like electric cooperatives originally brought power to farms in the 1930s and 1940s.
“People at the end of the line, people down on the river on the White River, people that were when we started this, having to go to McDonald’s parking lot to pick up Wi-Fi,” Coleman said. “That’s why we’re in this business.”
The electric division faces the traditional utility challenge: maintaining 5,000 miles of power lines across seven counties with a customer density half that of investor-owned utilities. March tornadoes destroyed 375 poles. Material costs keep climbing. Customer growth remains anemic.
Next, by contrast, operates in the booming broadband market. While electric service is a basic need with stable demand, high-speed internet is a growth industry. Rural customers who once had no options now gladly pay for speeds that match or exceed urban areas.
One customer testimonial in a Next promotional video captured the appeal: “In today’s world, you can live in the middle of nowhere if you have good internet.”
Looking Ahead
Both divisions face challenges ahead. Next plans to introduce multi-gigabit services and expand its offerings, but those federal grants that padded its profits will expire by 2032.
The electric division must cope with replacing coal plant power, upgrading aging infrastructure, and preparing for future storms without FEMA support—all while trying to keep rates affordable.
During a contentious moment in the meeting, member John Kunkel defended the cooperative’s overall performance: “There’s been a lot of stuff said that is not true that most of us know. NAEC and Next give back to the community in many, many ways.”
But the financial reality remains: One division is thriving while the other struggles, and regulations keep them from fully sharing their fortunes.
“We are not in Next to make tons of money,” Coleman said. “But it’s good that it is making money because what it has done…probably pushed back a rate increase for three years.”
For the 21,276 customers who enjoy both Next’s high-speed internet and NAEC’s electric service, the irony is hard to miss: The same poles carry both fiber and power lines, but only one service is profitable.